Info Page
Inspection codes for the Voice Inspection Scheduling System
Find the code for the inspection type you want, before you call our automated scheduling system.
The Voice Inspection Scheduling system is only for permits obtained Over-the-Counter at the Permit Center, In-House, or through the DBI Registered Contractor portal. The permit numbers will start with numbers.
For permits starting with letters obtained through the PermitSF portal, request inspections online.
Use these inspection codes when calling 628-652-3401 to book an inspection.
Electrical (EID) scheduling codes
- 100 - Rough cover/re-inspection
- 103 - Green tag - Energize service
- 105 - Orange tag - Energize temp service
- 109 - Survey
- 110 - Witness test (transfer to operator)
- 111 - Concrete encased electrode
- 117 - Long duration inspection (transfer to operator)
- 301 - Complete
- 302 - Complete with GT
- 307 - Witness test complete (transfer to operator)
Plumbing (PID) scheduling codes
- 100 - Gas tag request
- 101 - Survey inspection (transfer to operator)
- 105 - Complaint inspection (transfer to operator)
- 119 - More than one slot needed (transfer to operator)
- 200 - Underground dwv piping
- 201 - Underground domestic water piping
- 202 - Underground fire sprinkler service
- 208 - Boiler installation
- 212 - Radiant heat piping
- 213 - Building drain/sewer/house trap
- 228 - Shower pan installation
- 300 - Rough in drain, waste, and vent
- 302 - Rough in gas piping
- 304 - Rough in flues/vents/furnace
- 305 - Rough in fire sprinklers (transfer to operator)
- 320 - Rough in plumbing
- 400 - Final plumbing inspection
- 401 - Final mechanical inspection
- 402 - Final water heater
- 403 - Final furnace
- 404 - Final house trap/building sewer/storm sewer
Building (BID) scheduling codes
- 101 - Start work
- 106 - Final inspection
- 111 - Site verification
- 112 - Police permits - entertainment (transfer to operator)
- 113 - Fire permits - entertainment (transfer to operator)
- 120 - Forms
- 121 - Forms, partial
- 122 - Reinforcing steel/Rebar/Foundation/Concrete slab/Concrete pour/Piers/Shoring/Retaining wall/Anchor bolts
- 123 - Ok to pour
- 124 - Ceiling inspection
- 125 - Rough frame, partial
- 126 - Rough frame/Fire wall
- 127 - Insulation
- 129 - Shear wall/Plywood nailing
- 132 - Flues/vents/ducts (Fireplace/Grease shaft)
- 133 - Lath, exterior/Paper or Stucco wire
- 134 - Ok to cover/Interior lath
- 135 - Sheetrock nailing/Drywall nailing
- 142 - Pre-final
- 145 - Temporary certificate occupancy issued
- 146 - Mechanical
- 147 - Ceiling inspection, partial
- 153 - Ok to pour, partial
- 154 - Ok to cover, partial
- 200 - Long duration inspection (transfer to operator)