Sea Level Rise (SLR) Checklist
Fill out the SLR Checklist if your capital project is in the SLR Vulnerability Zone and costs more than $10 million.
Office of Resilience and Capital PlanningWhat to know
Requirements
Sea Level Rise Guidance for Capital Planning supports public departments and agencies assess the vulnerability, risk, and adaptive capacity of capital assets to sea level rise.
The purpose of this assessment is to develop City assets that are better prepared for rising sea levels and thereby protect lives, the environment, property, and public investment.
City departments must complete the Sea Level Rise Checklist if their project:
- Is in the Sea Level Rise (SLR) Vulnerability Zone
- Costs more than $10 million
The SLR Vulnerability Zone represents the area potentially inundated by a very high SLR scenario plus a 100-year storm in the year 2100.
What to know
Requirements
Sea Level Rise Guidance for Capital Planning supports public departments and agencies assess the vulnerability, risk, and adaptive capacity of capital assets to sea level rise.
The purpose of this assessment is to develop City assets that are better prepared for rising sea levels and thereby protect lives, the environment, property, and public investment.
City departments must complete the Sea Level Rise Checklist if their project:
- Is in the Sea Level Rise (SLR) Vulnerability Zone
- Costs more than $10 million
The SLR Vulnerability Zone represents the area potentially inundated by a very high SLR scenario plus a 100-year storm in the year 2100.
What to do
Check if your project is in the SLR vulnerability zone
Use the Sea Level Rise Data viewer to check if your project is located in the SLR vulnerability zone.
Complete the checklist
Fillout the SLR checklist:
- as soon as possible during the project’s planning and preliminary design phases
- no later than 30% design
You can usually complete the checklist when a project has defined objectives, scope, and scale.
Instructions and guidance
Send the completed checklist to:
Melissa Higbee, Resilience Program Manager
melissa.higbee@sfgov.orgNext steps
Review and approval process
We will review the checklist and obtain approval signatures from appropriate department contacts and the Capital Planning Committee.
You'll receive an email if we need additional information, or if your checklist is signed and approved.
Resubmitting your checklist
Departments are recommended to re-submit a revised checklist when projects have experienced major changes (for example, change in location or footprint, change in planning horizon, or change in adaptive capacity).